[The following information applies to the questions displayed below.] On July 23 of the current year, Dakota Mining Co. pays $4,715,000 for land estimated to contain 5,125,000 tons of recoverable ore. It installs and pays for machinery costing $410,000 on July 25. The company removes and sells 480,000 tons of ore during its first five months of operations ending on December 31. Depreciation of the machinery is in proportion to the mine’s depletion as the machinery will be abandoned after the ore is mined. Required: Prepare entries to record the following. (Do not round your intermediate calculations. Round "Depletion per ton" to two decimal places and round all other answers to the nearest whole dollar.) (a) The purchase of the land. (b) The cost and installation of machinery. (c) The first five months' depletion assuming the land has a net salvage value of zero after the ore is mined. (d) The first five months' depreciation on the machinery.

Answers

Answer 1
Answer:

Answer:

journal entries to make are as shown below: DAKOTA MINING CO

question 1

Date            Transaction                        Debit              credit             amount

July 23        land  purchase            Land account                        $ 4,715,000

july 23          land purchase                                           Bank       $ 4,715,000

question 2

July 25          Machine cost          machine account                     $410,000

July 25           Machine cost                                            bank        $410,000

December 31  depletion 5 months      profit                                $441,600

December 31   depletion                                         mine reserve   $0.92/ton

December 31    Depreciation               profit                                    $441,600

December 31,   depreciation                                    land                   $441,600                  

Explanation:

Purchase of fixed asset: the asset account usually have debit balances, so you debit the asset account and credit Dakota bank account where the money was paid out. The land account and  machine accout will have the purchase cost/installation cost as debit balances(entries) respectively while Dakota Mining co bank account will be credited with the respective amounts $ 4,715,000 -land purchase and $410,000- machine cost/installation.

The depletion quantity in 5 months was given. using ratio we extrapolate the depletion quantity was a full year as 1,152,000 QTY (12/5 X 480,000)

= 1,152,000 QTY the useful life of the mine is then calculated by dividing the reserve amount by the annual production of 1,152,000 = 4.448784 yrs

depreciation annually = divide cost of land by useful life = $1.059,840

5 months depreciation = 5/12  x annual depreciation = $441,600

depletion per ton is gotten as follows: divide $441,600 by 480,000 tons mined for 5 months = 0.92/ton depletion rate


Related Questions

The following data were taken from the records of Clarkson Company for the fiscal year ended June 30, 2017.Raw Materials Inventory 7/1/16 $51,100Factory Insurance $4,700Raw Materials Inventory 6/30/17 46,000Factory Machinery Depreciation 19,000Finished Goods Inventory 7/1/16 98,200Factory Utilities 29,100Finished Goods Inventory 6/30/17 26,100Office Utilities Expense 9,350Work in Process Inventory 7/1/16 26,800Sales Revenue 564,000Work in Process Inventory 6/30/17 22,300Sales Discounts 4,700Direct Labor 147,750Plant Manager’s Salary 65,600Indirect Labor 26,560Factory Property Taxes 9,810Accounts Receivable 27,100Factory Repairs 1,600Raw Materials Purchases 97,500Cash 35,600A) Prepare a cost of goods manufactured schedule (Assume all raw materials used were direct materials).B) Prepare an income statement through gross profitC) Prepare the current assets section of the balance sheet at June 30,2017
Net income or net loss for a period is calculated by the following formula
Sheffield's Bakery makes a variety of home-style cookies for upscale restaurants in the Atlanta metropolitan area. The company's best-selling cookie is the double chocolate almond supreme. Sheffield's recipe requires 10 ounces of a commercial cookie mix, 5 ounces of milk chocolate, and 1 ounce of almonds per pound of cookies. The standard direct materials costs are $0.80 per pound of cookie mix, $4 per pound of milk chocolate, and $19 per pound of almonds. Each pound of cookies requires 1 minute of direct labor in the mixing department and 5 minutes of direct labor in the baking department. The standard labor rates in those departments are $12.70 per direct labor hour (DLH) and $27 per DLH, respectively. Variable overhead is applied at a rate of $37.00 per DLH; fixed overhead is applied at a rate of $60 per DLH.Required:1. Calculate the standard cost for a pound of Sheffield's double chocolate almond supreme cookies. (Round answer to 2 decimal places, e.g. 3.51.)
Terra Company has two divisions, the Retail Division and the Wholesale Division. The following information was gathered for the two divisions for the current year: Retail Division Wholesale Division Operating income $ 7,500,000 $ 4,000,000 Operating assets $ 37,500,000 $ 17,500,000 Assuming that these are the only divisions of Terra Company, what is the ROI for the company as a whole?
The job search doesn’t end with the interview. After your interview, be sure to follow up with the appropriate correspondence and contact your references if necessary.After an interview, you are told that the company is unsure of when a decision will be made. Because you have some time and want to make the best impression, what advice should you follow when writing a thank-you letter to your interviewer?Check all that apply. O Send a separate letter to each interviewer. O Use a business letter format. O Mention something you liked about the interview. O Send thank-you letters to prospective coworkers. O Send a quick text to the interviewer

You have been asked to estimate the beta for a large South Korean company, with large holdings in steel and financial services. A regression of stock returns against the local market index yields a beta of 1.10, but the firm is 15% of the index. You have collected the average betas for global companies in each of the sectors, as well as the average debt equity ratios in each sector: Setor Average Regression Beta Average D/E ratio
Steel 1.18 30%
Financial
Services 1.14 70%
The average tax rate for these industries is 40%.
In the most recent period, the company you are analyzing earned 70% of its operating income from steel and 30% from financial services. The firm also had a debt/equity ratio of 150%, and a tax rate of 30%. Estimate the levered beta for the company.

Answers

Answer:

The levered beta for the company is 1.93.

Explanation:

Levered beta for the company = (Weight of steel business*levered beta of steel business) + (Weight of financial services business*levered beta of financial services business)

Levered beta of steel business = Unlevered beta of steel sector*[1+(1 - firm's tax rate)*(firm's debt/equity ratio)

levered beta of financial services business = Unlevered beta of financial services sector*[1+(1 - firm's tax rate)*(firm's debt/equity ratio)

Unlevered beta of steel sector = Current beta of steel sector/[1+(1 - avg. tax rate of firms in the sector)*(Avg. debt/equity ratio of the sector)  

Unlevered beta of steel sector = 1.18/[1+((1-0.4)*0.3)]

Unlevered beta of steel sector = 1.18/[1+(0.6*0.3)]

Unlevered beta of steel sector = 1.18/(1+0.18)

Unlevered beta of steel sector = 1.18/1.18

Unlevered beta of steel sector = 1

Levered beta of steel business = 1*[1+((1-0.3)*1.5)]

Levered beta of steel business = 1*[1+(0.7*1.5)]

Levered beta of steel business = 1*(1+1.05)

Levered beta of steel business = 1*2.05

Levered beta of steel business = 2.05

Unlevered beta of financial services sector = Current beta of financial services sector/[1+(1 - avg. tax rate of firms in the sector)*(Avg. debt/equity ratio of the sector)

Unlevered beta of financial services sector = 1.14/[1+((1-0.4)*0.7)]

Unlevered beta of financial services sector =1.14/[1+(0.6*0.7)]

Unlevered beta of financial services sector = 1.14/(1+0.42)

Unlevered beta of financial services sector = 1.14/1.42

Unlevered beta of financial services sector = 0.80

Levered beta of financial services business = 0.8*[1+((1-0.3)*1.5)] = 0.8*[1+(0.7*1.5)] = 0.8*(1+1.05) = 0.8*2.05 = 1.64

Levered beta for the company = (0.7*2.05) + (0.3*1.64)

Levered beta for the company = 1.44 + 0.49

Levered beta for the company = 1.93

Hence, the levered beta for the company is 1.93.

Final answer:

To estimate the levered beta for a company with operations in multiple sectors - steel and financial services in this case - you take a weighted average of the sector betas based on earnings distribution to get the unlevered beta. You then adjust for the company's debt/equity ratio and tax rate to get the levered beta. The estimated levered beta for this company is 2.378.

Explanation:

To estimate the levered beta for the company, we first need to consider the betas for each of the sectors the company operates in - steel and financial services. Given the firm's earnings distribution, the unlevered beta is computed as 0.7*Steel Beta + 0.3*Financial Services Beta = 0.7*1.18 + 0.3*1.14 = 1.16.

Next, to calculate the levered beta, we need to factor in the firm's debt/equity ratio. We use the formula for the levered beta: Levered Beta = Unlevered Beta * (1 + (1 - Tax Rate) * D/E ratio). Substituting the values we have: Levered Beta = 1.16 * (1 + (1 - 0.3) * 1.5) = 1.16 * 2.05 = 2.378. Therefore, the estimated levered beta is 2.378.

Learn more about Levered Beta Calculation here:

brainly.com/question/34082596

#SPJ11

Which of the following acronyms identifies the Big Five personality dimensions

Answers

The answer will be CANOE. Hope this helps:)

5. Garden Variety Flower Shop uses 750 clay pots a month. The pots are purchased at $2 each. Annual carrying costs per pot are estimated to be 30 percent of cost, and ordering costs are $20 per order. The manager has been using an order size of 1,500 flower pots. a. What additional annual cost is the shop incurring by staying with this order size

Answers

If Garden Variety Flower Shop uses 750 clay pots a month. The pots are purchased at $2 each. Annual carrying costs per pot are estimated to be 30 percent of cost, and ordering costs are $20 per order. The manager has been using an order size of 1,500 flower pots:

  • a. What additional annual cost is the shop incurring by staying with this order size will be: $105.24
  • b. What benefit would using the optimal order quantity yield will be 51.63%

a. Additional annual cost

Annual demand (D) =$750 x 12= $9,000

Ordering cost=$20 per order

Annual carrying costs(H)=0.30 ×$2.00 = $0.60

Order Quantity(Q) = 1,500

Find TC for Q

TC=Q÷2×H + D÷Q × S

TC=1,500÷2 × $0.60 + $9,000÷1,500×$20

TC=$450+$120

TC=$570............. (1)

Now find Qo

Qo=√2DS÷H

Qo=√2×$9,000×$20÷0.60

Qo=√600,000

Qo=$774.596

Qo=$774.60 (Approximately)

Find TC for Qo

TC=Q÷2×H + D÷Q ×

TC=774.60÷2 × $0.60 + $9,000÷774.60×$20

TC=$232.38+$232.38

TC=$464.76................(2)

Now let determine the additional annual cost

Additional annual cost=$570-$464.56

Additional annual cost=$105.24

b. Benefit would using the optimal order quantity yield (relative to the order size of 1,500)

Benefit=Qo÷Q

Benefit=$774.60÷1,500×100

Benefit=51.63%

The benefit is that about 51.63% of the storage space would be needed.

Learn more here:

brainly.com/question/19089832

Answer:

Additional cost= $570

Explanation:

Monthly demand = 750

Annual demand (D) = Monthly Demand x Number of months in a year

Annual demand (D) = 750 x 12 = 9,000

Cost (C) = $2.00 each

Annual carrying costs (Cc) = 30 percent of cost

Annual carrying costs (Cc) = 30% of $2.00 = $0.60

Ordering costs (Co) = $20

Current order quantity (Q1) = 1,500

Solution:

(a) Current cost is calculated as,

Current cost = Annual carrying costs + Annual ordering costs

Current cost = [(Quantity / 2) x Carrying cost] + [(Annual demand / Current Quantity) x Ordering cost]

Current cost = [(1500 / 2) x $0.60] + [(9000 / 1500) x $20]

Current cost = $450 + $120

Current cost = $570

An increase in the supply of capital will: Group of answer choices increase the real rental price of capital. decrease the real rental price of capital. increase the productivity of capital. decrease the real interest rate.

Answers

Answer:

The correct answer is letter "B": decrease the real rental price of capital.

Explanation:

The supply of capital increases when individuals and organizations have received more income out of their labor activities or production processes. As a result, the need for requesting loans will decrease. Thus, banks and financial institutions will decrease their interest rates to promote loans which will decrease the rental price of capital.

Sundar is preparing a research paper and has included the map above. His topic has to address negative externalities related to natural resources. Sundar is most likely writing a paper with which of the following titles?

Answers

Answer:

The possible topics for writing a research paper:

  • To write some research paper or perform any work related in order to address the negative externalities related to natural resources, Sundar must have some idea about the air pollution and its causes, as each person who wants to spread the idea about natural phenomenons or process must know about one of the most talk about terms including the environmental pollution and the factors that are causing it.
  • So, we can have our guess and the possible answer on which Sundar can write a research paper which might be, "Humanity spreads: air pollution and deforestation".

The answer to this question would be, Humanity Spreads: Air pollution and Deforestation.

Please note that it is useful to add the options provided with the question, in order to get an accurate answer and have your question answered quicker.

Hope this helps!!

Skyline Florists uses an activity-based costing system to compute the cost of making floral bouquets and delivering the bouquets to its commercial customers. Company personnel who earn $180,000 typically perform both tasks; other firm-wide overhead is expected to total $70,000. These costs are allocated as follows:Bouquet Production Delivery Other
Wages and salaries 60% 30% 10%
Other overhead 50% 35% 15%


Riverside anticipates making 20,000 bouquets and 4,000 deliveries in the upcoming year. The cost of wages and salaries and other overhead that would be charged to each bouquet made is closest to:

a. $12.50.
b. $7.15.
c. some other amount.
d. $8.75.
e. $13.75.

Answers

Answer:

b. $7.15

Explanation:

Cost of wages & salaries per bouquet = [($180,000*60%) + ($70,000*50%)] / 20,000

Cost of wages & salaries per bouquet = ($108,000 + $35,000) / 20,000

Cost of wages & salaries per bouquet = $143,000 / 20,000

Cost of wages & salaries per bouquet = $7.15

So, the cost of wages and salaries and other overhead that would be charged to each bouquet made will be $7.15.

Final answer:

The cost of wages and salaries charged to each bouquet is approximately $7.15.

Option (b) is true.

Explanation:

To find the cost of wages and salaries and other overhead allocated to each bouquet made, we can use the information provided for the allocation percentages for bouquet production.

Wages and Salaries allocated to bouquet production = 60%

Other overhead allocated to bouquet production = 50%

Now, let's calculate the costallocated to each bouquet:

Wages and Salaries for Bouquet Production:

Wages and Salaries = 60% of $180,000 (company personnel)

Wages and Salaries for Bouquet Production = 0.60 * $180,000 = $108,000

Other Overhead for Bouquet Production:

Other Overhead = 50% of $70,000 (other firm-wide overhead)

Other Overhead for Bouquet Production = 0.50 * $70,000 = $35,000

Now, add these two costs together to get the total cost allocated to bouquet production:

Total Cost Allocated to Bouquet Production = Wages and Salaries for Bouquet Production + Other Overhead for Bouquet Production

= $108,000 + $35,000

= $143,000

Now, we need to find the cost per bouquet. Given that Riverside anticipates making 20,000 bouquets in the upcoming year, divide the total cost allocated to bouquet production by the number of bouquets:

Cost per Bouquet = Total Cost Allocated to Bouquet Production / Number of Bouquets

Cost per Bouquet = $143,000 / 20,000 bouquets

Now, calculate the cost per bouquet:

Cost per Bouquet = $7.15

So, the cost of wages and salaries and other overhead allocated to each bouquet made is closest to $7.15.

The answer is (b) $7.15.

Learn more about Cost allocation here:

brainly.com/question/34659373

#SPJ3