The Model E extender fits with the 2 inch heavy duty hitches.The contract calls for 247 Model E extenders per week to be delivered in equal installments over the 16 weeks of the contract. The goal of Alpha Assemblies is to work 40 hours per week. The actual work time for completing the Model E extenders has been broken down by process in the table below. Also provided is the anticipated learning rate for each process. All processes must be performed in sequence and each step has its own separate and unique workcenter. To achieve the goal of working 40 hours per week or less, the cycle time must be lower than the takt time. What is the expected Cycle Time for Model E in Week 16? Note: learning is applied to the batch quantity per week. Do not try to break out the units within a week.Process Time Required per Unit Predecessor Task Learning RateA 9 82B 12 A 86C 18 B 81D 9 C 90E 12 D 80F 17 E 88G 14 F 83H 12 G 85I 8 H 82

Answers

Answer 1
Answer:

Answer:

Cycle Time = 10.19482 minute

Explanation:

From the question :

The Model E can be illustrated perfectly as shown below:

Process Time Required         Predecessor Task           Learning Rate

                per Unit

A                  9                                                                          82

B                 12                                     A                                  86

C                 18                                     B                                  81

D                 9                                      C                                  90

E                 12                                     D                                  80

F                 17                                     E                                   88

G                 14                                     F                                   83

H                 12                                     G                                  85

I                   8                                      H                                  82

Now For the minutes per week for each Process; we have :

Process Time Required         Predecessor      Learning      Minutes

                per Unit                    Task                   Rate               (Week 16)

A                  9                                                      82               4.069096

B                 12                           A                         86              6.564098

C                 18                          B                          81               7.74841

D                 9                           C                          90              5.9049

E                 12                           D                         80               4.9152

F                 17                            E                         88               10.19482

G                 14                           F                         83              6.644165

H                 12                           G                        85              6.264075

I                   8                            H                        82              3.616974

The objective here is to determine the expected Cycle Time for Model E in Week 16

So, we can equally regard the Cycle Time = Bottleneck of Activity for Week 16.

Cycle Time = 10.19482 minute   in as much as it is the the largest activity time for the week 16

Given that the demand per week is : = 247

The available time per week = 40 hours = 40 × 60 hours = 2400 minutes

Talk Time = Available Time Per Week/Demand Per Week

Talk Time = 2400/247

Talk Time = 9.716599

Thus; here  the cycle time is greater than the talk time.


Related Questions

Your order is supposed to be delivered between 5PM-6PM, and it’s now 5:45PM. You’re stuck in a long line waiting to check out. In this situation, you will be late delivering the order. Provide an example of the text message you would send to the member.
In leading the push for proficient strategy execution and operating excellence, top-level managers need to take the lead on all of the following EXCEPT:_________a. being out in the field and seeing how well operations are going.b. delegating authority to middle and lower-level managers and creating a sense of empowerment among employees to move the implementation process forward.c. gathering information firsthand and gauging the progress beingmade.d. learning the obstacles in the path of good execution and clearing the way for progress.e. holding periodic ceremonies to honor people who excel in displaying the company values and ethical principles.
The best cost system to use for a company producing a continuous stream of similar items would be a: Group of answer choices Production costing system. Job order system. No cost system is required when jobs are similar. Process costing system.
You decided to buy apples at a grocery store somewhere in the mountains. You buy 5 pounds of apples, which are sold for $1.99/lb. (One pound is the unit of force equal to 0.454 kgx9.80 m/s where g = 9.80 m/s2 is the standard value of the acceleration due to the gravity). You overpaid for the apples, since the value of the acceleration due to the gravity at this mountain location is only gmountain 9.79 mis. Determine how much you overpaid for your 5 pounds of apples.
Perfect Clean, Inc. provides housekeeping services. The following financial data have been provided.Service Revenue$80,000Cleaning Supplies Used22,000Wages Expense19,350Office Rent Expense5,150Depreciation Expense—Machinery550Calculate the contribution margin and the contribution margin ratio. (Round your contribution margin to the nearest dollar, and your contribution margin ratio to two decimal places.)A) $38,650; 48.31% B) $74,850; 93.56%C) $60,650; 75.81% D) $32,950; 41.19%

If the tax elasticity of labor supply is 0.16, by what percentage will the quantity of labor supplied increase in response to Instructions: In part b, enter your response as a percentage rounded to one decimal place. a. A $500 per person income tax rebate check? A 4.5% increase A 2% increase A 1.5% increase No increase b. A reduction of 5 percent in marginal tax rates?

Answers

Answer:

If every work receives a tax rebate of $500 per person income tax the quantity of labor supplied will not increase because the rebate is a temporary

A 4.5% increase in marginal tax  = 0.16 * 4.5 = 0.72  = 0.7 ( decrease in quantity of labor )

A 2% increase in marginal tax

= 0.16 * 2 = 0.32 = 0.3 ( decrease in quantity of labor )

A 15% increase

= 0.16 * 15 = 2.4 ( decrease in quantity of labor )

No increase = 0.16 = 0.16 ( quantity of labor supplied remains unchanged )

A reduction of 5%

= 0.16 * 5 =  0.8 ( increase in quantity of labor )

Explanation:

Tax elasticity of labor supply = 0.16

What percentage will the quantity of labor supplied increase in response to

A) $500  per person income tax rebate

percentage change in quantity supplied = (tax elasticity of supply) * (percentage change in tax rate ) If every work receives a tax rebate of $500 per person income tax the quantity of labor supplied will not increase because the rebate is a temporary measure and does not have an effect the tax rate in the long run.

B) A 4.5% increase in marginal tax

change in the quantity of labor = tax elasticity * increase marginal tax

                                               0.16 * 4.5 = 0.72  = 0.7 ( decrease in quantity of labor )

A 2% increase in marginal tax

= 0.16 * 2 = 0.32 = 0.3 ( decrease in quantity of labor )

A 15% increase

= 0.16 * 15 = 2.4 ( decrease in quantity of labor )

No increase = 0.16 = 0.16 ( quantity of labor supplied remains unchanged )

A reduction of 5%

= 0.16 * 5 =  0.8 ( increase in quantity of labor )

This​ year, Druehl,​ Inc., will produce 60 comma 000 hot water heaters at its plant in​ Delaware, in order to meet expected global demand. To accomplish​ this, each laborer at the plant will work 160 hours per month. If the labor productivity at the plant is 0.15 hot water heaters per labor​ hour, how many laborers are employed at the​ plant?

Answers

Answer:

The answer is: 2500 employees

Explanation:

Giving the following information we need to calculate the number of employees:

Total production= 60000

Hours per worker= 160 hours

labor productivity= 0,15

It takes to a single employee= 1/0,15= 6,67 hours to make a heater.

Each worker produces=160/6,67=24 heaters a year.

Now we can calculate the number of workers:

60000/24= 2500 employees

An company buys a color printer that will cost $18,000 to buy, and last 5 years. It is assumed that it will require servicing costing $500 each year. What is the equivalent annual annuity of this deal, given a cost of capital of 12%? A. -$3983 B. -$4002 C. -$4957 D. -$5493

Answers

Answer:

The correct answer is option (D)

Explanation:

Solution

Given that:

The present value of equity factor for 5 years at 12% discount are = 3.60478

Then,

The present value of servicing costing = -$500 * 3.60478 = -$1802.39

Thus,

The present value of cost to buy =- $18000

The total Present value = -18000 + 1802.39 = -$19802.39

So,

The equivalent annual annuity = total Present value / present value of equity factor

= -$19802.39 / 3.60478

= -$5493.37

Therefore, the equivalent annual annuity of this deal is -$5493.37

In the situation described in the above question, suppose that the Central Bank of Vietnam decides to keep the nominal dong-dollar exchange rate constant indefinitely. Given whatDEP Inc. has determined about the trend in the real exchange rates and assuming that the rate of inflation in the rest of the world remains unchanged, what should one expect to happen to the rate of inflation in Vietnam over the next several years compared to the past?

Answers

Options:

a.The rate of inflation will rise.

b.The rate of inflation will decline.

c.The rate of inflation will remain unchanged.

d.The rate of inflation may rise or decline

Answer:b.The rate of inflation will decline.

Explanation:Fixed exchange rate is a term used in Economics to describe the "pegging" or fixes the amount to which its own currency will trade with a popular currency like the United States Dollar. This will give investors,importers and exporters more stability and confidence as they will not be scared of indiscriminate fluctuations. WITH THIS CONFIDENCE THE RATE OF INFLATION WILL DECLINE AS INVESTORS WILL NOT BE UNDER PRESSURE TO HOARD GOODS OR REDUCE THE VOLUME OF PRODUCTS RELEASED TO THE MARKET AND CONSUMERS WILL NOT BE UNDER PRESSURE TO BUY.

Given the following data, calculate the Total Variable Cost variance. Planning Budget Actual Results Revenue $73,000 $75,000 Variable costs $23,000 $20,000 Contribution margin $50,000 $55,000 Fixed costs $15,000 $10,000 Profit before taxes $35,000 $45,000 a. $3,000 Favorable b. $3,000 Unfavorable c. $5,000 Favorable d. $5,000 Unfavorable e. $2,000 Unfavorable f. $2,000 Favorable

Answers

Answer:

a. $3,000 Favorable

Explanation:

Variable cost variance is the difference between the budgeted variable cost and actual variable cost for a period.

Use following formula to claculate the variable cost variance

Variable cost variance = Budgeted Variable cost - Actual variable cost

Placing values in the formula

Variable cost variance = Budgeted Variable cost - Actual variable cost

Variable cost variance = $23,000 - $20,000

Variable cost variance = $3,000

As the actual cost is less than the budgeted cost, so the $3,000 is saved in respect of variable cost.

Autoliv in Ogden, Utah creates airbags. The deployment time of an airbag should be between 21 and 27 milliseconds and their current average is 22 milliseconds with a standard deviation of 0.25 milliseconds. Determine the process capability index if they were to center the mean.

Answers

Answer:

4

Explanation:

The calculation of the process capability index is given below

Data provided in the question according to the question is as follows

USL = 27

LSL = 21

Now we take the average

X = (21 +27) ÷ 2

= 24

The standard deviation is 0.25

= min(USL - mean ÷ 3 × standard deviation , mean - LSL ÷ 3 × standard deviation)

After solving this the process capability index is 4